Bunker construction is well under way. Most of the bunkers are dug out and they have started repairing all of the slopes in the bunkers so we don't have 2 feet of sand in the faces.

There is more fill work than we expected to correct the faces but at least the fill material is a quarter of the cost compared to the bunker sand. You have to fill the faces with either one - and doing it in the sub base will result in a properly constructed bunker.