So far the greens have been much deeper that expected to fill in and repair. The river greens were averaging about 16-18" of mix when it should be 12". It is just taking more fill material than expected to repair these bases. Not a big deal buy just a little more material needed than expected.

This is a picture of 14 before we started fixing the bottoms. These drain lines will be filled in and the bottom will be brought up to where it needs to be.